Total investment of 152.7 billion yuan! Hulunbeier intends to build 10 tens of billions of new energy projects

April 3, Hulunbeier People's Government disclosed the city's 10 billion project planning action specifics. As of April 1, the city plans to promote more than 10 billion yuan 33 key projects, with a total investment of 604.2 billion yuan. Project categories cover traditional energy,new energy, grid engineering, etc.

From the preliminary plan, there have been 28 projects to start the preliminary work, 5 projects are in the planning stage. Among them, there are 10 projects related to new energy, with a total project investment of 152.7 billion yuan.

See below for details:

Yakeshi wind and storage integration base project. Total project investment of 17.6 billion yuan, the project adopts the "pumped storage + wind + photovoltaic" mode, to create a multi-energy complementary clean energy base in Yakeshi, is conducive to the realization of decarbonization, and improve the overall level of utilization of renewable energy. Currently the project is in the planning stage, the next step, to be pumped storage power plant project after the start of construction, synchronized with the investment promotion work, as soon as possible to clarify the implementation of the main body to speed up the relevant procedures.

Shanxi Electric Power Construction Co., Ltd. 2 million kilowatts of wind power hydrogen integration and downstream chemicals production project. The total investment of the project is 25.8 billion yuan, and the project unit is China Energy Construction Group Shanxi Electric Power Construction Co. Has signed a cooperation agreement, is carrying out the feasibility study report preparation of the research work. The next step is to plan to start the preparation of the feasibility study report, determine the project site, and promote the project's preliminary formalities; the second is to actively coordinate the downstream product sales channels.

Shanxi international energy wind power system 350,000 tons of green aviation kerosene project. The total investment of the project is 10.7 billion yuan, and the project unit is Jin Reserve (Arongqi) New Energy Co. Has completed the project technical program review, the preparation of the completion of the project declaration. To be declared after the success of the chemical concentration area to carry out Shanxi International Energy wind power system 350,000 tons of green aviation kerosene project declaration. The next step, because of the Arong Banner will be re-declared chemical concentration area adjusted to the distance from the Arun River 1 kilometer outside, the need to re-compile the chemical concentration area of the master plan, fire special planning, planning and environmental impact assessment and other 14 related planning, reports, it is recommended to coordinate the autonomous region of the Office of the Ministry of Industry and Information Technology of the Arong Banner Chemical Concentration Area to give support to the work of the declaration.

Guoneng Inner Mongolia Mengdong 2 × 600,000 kilowatts of coal power (stock) +2.4 million kilowatts of new energy (new) "two joint venture" integration project. The total investment of the project is 12.4 billion yuan. Fan, booster site location has completed the macro site selection, integrated planning program, research, consumption analysis report has been completed, "two joint venture" integration project has completed the national assessment, the project has not yet started to declare work. The next step is to strive for inclusion in the national and regional "Tenth Five-Year Plan" project list; second is to actively coordinate with the autonomous region's energy bureau for construction indicators.

Huaneng Lingdong Base Phase III Moqi 2 million kilowatts wind power project. The total investment of the project is 10 billion yuan. Has completed the preparation of the project implementation program and site selection subversive factors, start construction time to be determined. The next step is to strive for inclusion in the national and regional "Tenth Five-Year Plan" project list; second is to actively coordinate with the autonomous region's energy bureau for construction indicators.

New Energy Hydrogen Generation Project in Yimin High-carrying Energy Park. The project has a total investment of 12 billion yuan, and the project unit is Huaneng Yimin Coal & Power Co. Is preparing the design program, to carry out the project feasibility of preliminary research, to have the conditions to start the project declaration work, start construction time to be determined. The next step is to study the path of project declaration. The second is to consult with coal chemical enterprises on the supply of green hydrogen.

Huaneng Yimin Power Plant Wind-Guang-Fire-Storage Multi-energy Complementary Integration Project. The total investment of the project is 13.5 billion yuan. Has signed a framework agreement on cooperation in the development of new energy bases, is carrying out restrictive factors checking, while coordinating with the Northeast Division of the State Grid to issue opinions on grid support. The next step is to study the path of the project declaration; secondly, according to the latest policy and restrictive factors checking opinions, avoid restrictive factors, modify the declaration program; thirdly, coordinate the project approval to obtain the support of the Autonomous Region Energy Bureau.

Hulunbeier 12 million kilowatts of extra-high voltage transmission supporting new energy base project. The project has a total investment of 30 billion yuan. Currently in the planning stage, has not yet carried out preliminary work, start construction time to be determined. The next step, to be determined after the main body of the construction, to carry out the preparation of research, filing, environmental assessment, water protection, overburdened mines, flood assessment, construction land indexes, permits for the commencement of construction and other preliminary work to promote.

2 million kilowatts of photovoltaic development project in Xinbalhuzuo Banner. Project total investment of 10 billion yuan. 2023, preliminary and JA Solar Investment (China) Limited, CLP Sichuan Investment Green Energy (Chengdu) Limited, Inner Mongolia Energy Group Limited Industrial Development Branch signed a cooperation framework agreement, and complete the land subversive factors investigation work, has not yet obtained the construction indicators. The next step, first, is docking, looking for construction indicators competitive enterprise development and construction, to achieve the overall scale of 2 million kilowatts; second is to coordinate the regional energy bureau for construction indicators.

Huaneng Xinbaerhu Rouge Banner Border Wind, Fire and Storage 2 Million Kilowatts Integrated Multi-energy Complementary Base Project. The total investment of the project is 10.7 billion yuan, and the project unit is Huaneng Inner Mongolia Mengdong New Energy Co. Has completed the project planning and site selection, construction program preparation, site subversive factors investigation, the new right flag people's government and enterprises have signed a development agreement. Has coordinated the State Grid Hulunbeier Power Supply Company will be included in the project "Tenth Five-Year" power planning, with project reporting conditions. Plans to start construction in 2027, completed in 2028. The next step, to be carried out by the National Energy Board of the country's fourth batch of large bases to declare the work of coordinating regional energy bureau to the National Energy Board for review.

Special notice: Goodhao is reproduced from other websites for the purpose of transmitting more information rather than for profit, and at the same time does not mean to endorse its views or confirm its description, the content is for reference only. Copyright belongs to the original author, if there is infringement, please contact us to delete.